Thanks to Jeff Miller for sending this timetable to us so we can see how things will progress with this new development area.
ANTICIPATED TIMETABLE FOR CREATION OF GATEWAY SOUTH ECONOMIC DEVELOPMENT AREA
May 23, 2013
June 13, 2013 Gateway South Neighborhood Meeting at University of Indianapolis
July 8, 2013 Attorney Bruce Donaldson submits Declaratory Resolution to DMD staff
July 17, 2013 Approval of Declaratory Resolution by Metropolitan Development Commission (MDC) [Need Neighborhood stakeholders to participate in presentation]
July 31, 2013 Attorney Bruce Donaldson drafts Council Proposal
August 9, 2013 Chris Jolivette submits Council Proposal to the Council Office
August 19, 2013 Introduction of Council Resolution at City-County Council Meeting
August 26, 2013 Council Metropolitan & Economic Development Committee Meeting [Need
Neighborhood stakeholders to participate in presentation]
September 9, 2013 Passage by City-County Council [Need Neighborhood stakeholders to attend Council meeting]
September 18, 2013 Attorney Bruce Donaldson drafts MDC Confirmatory Resolution & delivers to DMD staff
September 25, 2013 Hand Delivery of Notices (Newspapers- Bruce Donaldson & hand delivery- Steve Schulmeyer)
Delivery of Confirmatory Resolution by DMD Staff
October 16, 2013 Public Hearing & Confirmatory Resolution approved by MDC [Need
Neighborhood stakeholders to participate in presentation]